«Leaders Guide Trenching and Shoring Safety - Competent Person The manual for Excavations Trenching and Shoring is produced in Adobe Acrobat. The ...»

-- [ Page 10 ] --

(2) Where the competent person finds evidence of a situation that could result in a possible cave-in, indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions, exposed employees shall be removed from the hazardous area until the necessary precautions have been taken to ensure their safety.

(l) Fall protection.

(1) Where employees or equipment are required or permitted to cross over excavations over 6-feet in depth and wider than 30 inches, walkways or bridges with standard guardrails shall be provided.

(2) Adequate barrier physical protection shall be provided at all remotely located excavations. All wells, pits, shafts, etc., shall be barricaded or covered. Upon completion of exploration and other similar operations, temporary wells, pits, shafts, etc., shall be backfilled.

General Materials (GM) - References, Annotations, or Tables Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code; and Section 4216, Government Code.

The above information is provided free of charge by the Department of Industrial Relations from its web site at www.dir.ca.gov.

Protection of Employees in Excavations Requirements for Protective Systems §1541.1. Requirements for Protective Systems. (a) Protection of employees in excavations.

(1) Each employee in an excavation shall be protected from cave-ins by an adequate protective system designed in accordance with Section 1541.1(b) or (c)

except when:

(A) Excavations are made entirely in stable rock; or (B) Excavations are less than 5 feet in depth and examination of the ground by a competent person provides no indication of a potential cave-in.

(2) Protective systems shall have the capacity to resist without failure all loads that are intended or could reasonably be expected to be applied or transmitted to the system.

(b) Design of sloping and benching systems. The slopes and configurations of sloping and benching systems shall be selected and constructed by the employer or his designee and shall be in accordance with the requirements of Section 1541.1(b)(1), Section 1541.1(b)(2), Section 1541.1(b)(3), or Section 1541.1(b)(4),

as follows:

(1) Option (1) --Allowable configurations and slopes.

(A) Excavations shall be sloped at an angle not steeper than one and one-half horizontal to one vertical (34 degrees measured from the horizontal), unless the employer uses one of the other options listed below.

(B) Slopes specified in Section 1541.1(b)(1)(A) shall be excavated to form configurations that are in accordance with the slopes shown for Type C soil in Appendix B to this article.

(2) Option (2) --Determination of slopes and configurations using Appendices A and B. Maximum allowable slopes, and allowable configurations for sloping and benching systems, shall be determined in accordance with the conditions and requirements set forth in Appendices A and B to this article.

(3) Option (3) --Designs using other tabulated data.

(A) Designs of sloping or benching systems shall be selected from and be in accordance with tabulated data, such as tables and charts.

(B) The tabulated data shall be in written form and shall include all of the

following:

1. Identification of the parameters that affect the selection of a sloping or benching system drawn from such data;

2. Identification of the limits of use of the data, to include the magnitude and configuration of slopes determined to be safe;

3. Explanatory information as may be necessary to aid the user in making a correct selection of a protective system from the data.

4. At least one copy of the tabulated data which identifies the registered professional engineer who approved the data, shall be maintained at the jobsite during construction of the protective system. After that time the data may be stored off the jobsite, but a copy of the data shall be made available to the Division upon request.

(4) Option (4) --Design by a registered professional engineer.

(A) Sloping and benching systems not utilizing Option (1) or Option (2) or Option (3) under Section 1541.1(b) shall be stamped and signed by a registered professional engineer.

(B) Designs shall be in written form and shall include at least the following:

1. The magnitude of the slopes that were determined to be safe for the particular project;

2. The configurations that were determined to be safe for the particular project;

3. The identity of the registered professional engineer approving the design.

(C) At least one copy of the design shall be maintained at the jobsite while the slope is being constructed. After that time the design need not be at the jobsite, but a copy shall be made available to the Division upon request.

(c) Design of support systems, shield systems, and other protective systems.

Designs of support systems, shield systems, and other protective systems shall be selected and constructed by the employer or his designee and shall be in accordance with the requirements of Section 1541.1(c)(1); or, in the alternative, Section 1541.1(c)(2); or, in the alternative, Section 1541.1(c)(3); or, in the

alternative, Section 1541.1(c)(4) as follows:

(1) Option (1) --Designs using Appendices A, C and D. Designs for timber shoring in trenches shall be determined in accordance with the conditions and requirements set forth in Appendices A and C to this article. Designs for aluminum hydraulic shoring shall be in accordance with Section 1541.1(c)(2), but if manufacturer's tabulated data cannot be utilized, designs shall be in accordance with Appendix D.





(2) Option (2) --Designs Using Manufacturer's Tabulated Data.

(A) Design of support systems, shield systems, or other protective systems that are drawn from manufacturer's tabulated data shall be in accordance with all specifications, recommendations, and limitations issued or made by the manufacturer.

(B) Deviation from the specifications, recommendations, and limitations issued or made by the manufacturer shall only be allowed after the manufacturer issues specific written approval.

(C) Manufacturer's specifications, recommendations, and limitations, and manufacturer's approval to deviate from the specifications, recommendations, and limitations shall be in written form at the jobsite during construction of the protective system. After that time this data may be stored off the jobsite, but a copy shall be made available to the Division upon request.

(3) Option (3) --Designs using other tabulated data.

(A) Designs of support systems, shield systems, or other protective systems shall be selected from and be in accordance with tabulated data, such as tables and charts.

(B) The tabulated data shall be in written form and include all of the following:

1. Identification of the parameters that affect the selection of a protective system drawn from such data;

2. Identification of the limits of use of the data;

3. Explanatory information as may be necessary to aid the user in making a correct selection of a protective system from the data.

(C) At least one copy of the tabulated data, which identifies the registered professional engineer who approved the data, shall be maintained at the jobsite during construction of the protective system. After that time the data may be stored off the jobsite, but a copy of the data shall be made available to the Division upon request.

(4) Option (4) --Design by a registered professional engineer.

(A) Support systems, shield systems, and other protective systems not utilizing Option 1, Option 2, or Option 3, above, shall be approved by a registered professional engineer.

(B) Designs shall be in written form and shall include the following:

1. A plan indicating the sizes, types, and configurations of the materials to be used in the protective system; and

2. The identity of the registered professional engineer approving the design.

(C) At least one copy of the design shall be maintained at the jobsite during construction of the protective system. After that time, the design may be stored off the jobsite, but a copy of the design shall be made available to the Division upon request.

(d) Materials and equipment.

(1) Materials and equipment used for protective systems shall be free from damage or defects that might impair their proper function.

(2) Manufactured materials and equipment used for protective systems shall be used and maintained in a manner that is consistent with the recommendations of the manufacturer, and in a manner that will prevent employee exposure to hazards.

(3) When material or equipment that is used for protective systems is damaged, a competent person shall examine the material or equipment and evaluate its suitability for continued use. If the competent person cannot assure the material or equipment is able to support the intended loads or is otherwise suitable for safe use, then such material or equipment shall be removed from service, and shall be evaluated and approved by a registered professional engineer before being returned to service.

(e) Installation and removal of supports.

(1) General.

(A) Members of support systems shall be securely connected together to prevent sliding, falling, kickouts, or other predictable failure.

(B) Support systems shall be installed and removed in a manner that protects employees from cave-ins, structural collapses, or from being struck by members of the support system.

(C) Individual members of support systems shall not be subjected to loads exceeding those which those members were designed to withstand.

(D) Before temporary removal of individual members begins, additional precautions shall be taken to ensure the safety of employees, such as installing other structural members to carry the loads imposed on the support system.

(E) Removal shall begin at, and progress from, the bottom of the excavation.

Members shall be released slowly so as to note any indication of possible failure of the remaining members of the structure or possible cave-in of the sides of the excavation.

(F) Backfilling shall progress together with the removal of support systems from excavations.

(2) Additional requirements for support systems for trench excavations.

(A) Excavation of material to a level no greater than 2 feet below the bottom of the members of a support system shall be permitted, but only if the system is designed to resist the forces calculated for the full depth of the trench, and there are no indications while the trench is open of a possible loss of soil from behind or below the bottom of the support system.

(B) Installation of a support system shall be closely coordinated with the excavation of trenches.

(f) Sloping and benching systems. Employees shall not be permitted to work on the faces of sloped or benched excavations at levels above other employees except when employees at the lower levels are adequately protected from the hazard of falling, rolling, or sliding material or equipment.

(g) Shield systems.

(1) General.

(A) Shield systems shall not be subjected to loads exceeding those which the system was designed to withstand.

(B) Shields shall be installed in a manner to restrict lateral or other hazardous movement of the shield in the event of the application of sudden lateral loads.

(C) Employees shall be protected from the hazard of cave-ins when entering or exiting the areas protected by shields.

(D) Employees shall not be allowed in shields when shields are being installed, removed, or moved vertically.

(2) Additional requirements for shield systems used in trench excavations. The sides of the shield shall extend a minimum of 18 inches above the vertical walls of compound excavations as shown in Appendix B, figures B-1, B-1.2 and B-1.3.

On vertically cut trenches, the shield shall extend to at least the catch point of the trench. Excavations of earth material to a level not greater than 2 feet below the bottom of a shield shall be permitted, but only if the shield is designed to resist the forces calculated for the full depth of the trench, and there are no indications while the trench is open of a possible loss of soil from behind or below the bottom of the shield.

(h) Uprights shall extend to the top of the trench with the lower end of the upright not more than 2 feet from the bottom of the trench.

NOTE: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.

Appendix A http://www.dir.ca.gov/title8/1541_1a.html Appendix B http://www.dir.ca.gov/title8/1541_1b.html Appendix C http://www.dir.ca.gov/title8/1541_1c.html Appendix D http://www.dir.ca.gov/title8/1541_1d.html Appendix E http://www.dir.ca.gov/title8/1541_1e.html Appendix F http://www.dir.ca.gov/title8/1541_1f.html Article 6 Table of Contents: http://www.dir.ca.gov/title8/sb4a6.html http://www.dir.ca.gov/samples/search/query.htm

–  –  –

Appendix A Soil Classification §1541.1. Requirements for Protective Systems, Appendix A (a) Scope and application.

(1) Scope. This appendix describes a method of classifying soil and rock deposits based on site and environmental conditions, and on the structure and composition of the earth deposits. The appendix contains definitions, sets forth requirements, and describes acceptable visual and manual tests for use in classifying soils.

(2) Application. This appendix applies when a sloping or benching system is designed in accordance with the requirements set forth in Section 1541.1(b)(2) as a method of protection for employees from cave-ins. This appendix also applies when timber shoring for excavations is designed as a method of protection from cave-ins in accordance with Appendix C to this article, and when aluminum hydraulic shoring is designed in accordance with Appendix D. This appendix also applies if other protective systems are designed and selected for use from data prepared in accordance with the requirements set forth in Section 1541.1(c), and the use of the data is predicated on the use of the soil classification system set forth in this appendix.

(b) Definitions.

Cemented soil: A soil in which the particles are held together by a chemical agent, such a calcium carbonate, such that a hand-size sample cannot be crushed into powder or individual soil particles by finger pressure.



Pages:     | 1 |   ...   | 8 | 9 || 11 | 12 |   ...   | 13 |


Similar works:

«1 On the Mode of the Semantic Changes of Body-part Terms in English and Chinese -Illustrated by the Examples of the Lexical Items “Hand” and “Shou” in the Holy Bible. Wang Min & Wang Wenbin (College of Foreign Languages, Shaoxing University, Shaoxing, Zhejiang, 312000;Institute of Theoretical Linguistics, Ningbo University, Ningbo, Zhejiang, 315211) Abstract: By applying the prototype theory and Taylor’s meaning chain mode, this paper proves that the path of the semantic changes of...»

«Fernerkundung / Naturschutz Literaturzusammenstellung aus der zentralen Literaturdatenbank des Bundesamtes für Naturschutz DNL-online – Stand: 23. Dezember 2014 – Hinweise Veröffentlichungsjahre der Publikationen: 1971-2014 Anzahl der Zitate: 257 Suchstrategie: Schlagworte: fernerkundung (naturschutz* o landschaftspflege o *schutzgebiet*) Sortierung: chronologisch absteigend 1. Signatur: BONN Zss Edelkastanie II / Bernd-Gunther Encke [Red.]. Abb.; Tab.; Lit. In: AFZ / Der Wald :...»

«T.C. Memo. 2012-62 UNITED STATES TAX COURT JOHN KELLER, ACTION AUTO BODY, Petitioner v. COMMISSIONER OF INTERNAL REVENUE, Respondent Docket No. 28991-09. Filed March 8, 2012. R determined that 10 of P’s workers were employees rather than independent contractors, and determined employment taxes and penalties against P. Held: Seven of 10 workers listed in the notice of determination of worker classification were independent contractors, and 3 were employees. Held, further, P is liable for an...»

«LEGISLATING DIGITAL EXHAUSTION Aaron Perzanowski † & Jason Schultz †† ABSTRACT The digital shift in distribution, from markets premised on disposing of physical artifacts to markets defined by data flows, is among the most important changes in the copyright landscape since the enactment of the 1976 Copyright Act. The disconnect between this new reality and our current statutory rules is particularly evident when it comes to the question of exhaustion. The first sale doctrine embodied...»

«Fools for Christ’s Sake Madness, mission, and the Kingdom of God in south Wellington Richard Noble Fools for Christ’s Sake: Madness, mission, and the Kingdom of God in South Wellington Richard Noble A paper presented to the Theology, Disability, and the People of God conference, Carey Baptist College, Auckland, New Zealand, 1-3 July 2013. Multi-psycho-schizo-mani-phobia neurosis Even though the sound of it is something quite atrocious If you say it long enough, you’ll know your diagnosis...»

«Bummis Care Pack Essential information to keep, to ensure your success in using and washing cloth diapers!1. Wrap Comparison Chart 2. Bummis’ Very Simple Washing Method 3. Detergent Information 4. Residues 5. Tips & Troubleshooting 6. Bummis Warranty 7. Tots Bots Washing & Warranty 8. How to Fold a Prefold Diaper! 4300 St-Laurent blvd suite 200 Montreal QC H2W 1Z3 • 1-888-828-6647 • www.bummis.com • info@bummis.com VERY SIMPLE METHOD FOR WASHING CLOTH DIAPERS A NOTE ABOUT WASHING...»

«Canada Europe India Israel Latin America Morocco United Kingdom United States Charter of the International Jewish anti-Zionist Network September 29, 2008 The building of the International Jewish anti-Zionist Network, and the writing of its founding Charter, was made possible by the participation and the contributions of: Reuven Abergel Sue Goldstein Ilan Pappé Lisa Adler Yali Hashash Flo Razowsky Gabriel Ash Tikva Honig-Parnass Lisa Rofel Ryvka Bar Zohar Selma James Eric Romann Perry...»

«25 May 2016 Trust in water Water 2020: Regulatory framework for wholesale markets and the 2019 price review Appendix 1 Securing legitimacy of future price controls further evidence and analysis www.ofwat.gov.uk Water 2020: Regulatory framework for wholesale markets and the 2019 price review Appendix 1 Securing legitimacy of future price controls further evidence and analysis Contents 1. Introduction 2 2. Approach to the impact assessment and our analysis of impacts 4 3. Assessment by impact...»

«! MASTERARBEIT / MASTER’S THESIS Titel der Masterarbeit / Title of the Master’s Thesis “Walmart’s Withdrawal from the German Market” verfasst von / submitted by Ameli Mayr Angestrebter akademischer Grad / in partial fulfilment of the requirements for the degree of Master of Science (MSc) Wien, 2015 / Vienna 2015 Studienkennzahl lt. Studienblatt / A 066914 degree program code as it appears on the student record sheet: Studienrichtung lt. Studienblatt / Master in International...»

«USAGE OF A DATA-LOGGING DEVICE WITH ADDITIONAL SENSORS FOR A LARGE FIELD OPERATIONAL TEST David Sánchez Active Safety Responsible, CTAG david.sanchez@ctag.com Tel: +34 986 900 300 (ext. 454); Fax: +34 986 900 301 Marga Sáez Active Safety Researcher, CTAG marga.saez@ctag.com Clément Val Experiments & Human Behaviour Science Responsible, CEESAR clement.val.ceesar@gmail.com Dipl.-Ing. Mohamed Benmimoun Institut für Kraftfahrzeuge, RWTH Aachen University (IKA) mbenmimoun@ika.rwth-aachen.de...»

«Newmont Ghana Gold Ltd.GUIDE TO LAND ACQUISITION AND COMPENSATION FOR EXPLORATION ACTIVITIES AHAFO GOLD PROJECT OCTOBER 2005 BRONG AHAFO REGION GHANA WEST AFRICA GUIDE TO LAND ACQUISITION AND COMPENSATION FOR EXPLORATION ACTIVITIES AT THE NEWMONT GHANA GOLD LTD. AHAFO PROJECT Prepared by: Newmont Ghana Gold Ltd. C825/26 Lagos Avenue East Legon, Accra, Ghana October 2005 INTRODUCTION The Ahafo Project is located northwest of Accra, the capital of Ghana, in the Brong-Ahafo Region, between the...»

«The Incompetent Atheist or, There is no God and Darwin is his Prophet Richard Dawkins, The God Delusion, 2006 Before starting The God Delusion I made a prediction, based on some reading of Dawkins’s earlier works. I expected the argument to have the following steps: The question whether God exists is the first question in religion. It is a question like any other about existence, to be answered by evidence. All evidence of existence is scientific. There is no evidence for the existence of...»





 
<<  HOME   |    CONTACTS
2016 www.thesis.xlibx.info - Thesis, documentation, books

Materials of this site are available for review, all rights belong to their respective owners.
If you do not agree with the fact that your material is placed on this site, please, email us, we will within 1-2 business days delete him.